Construction Update from Developer Milender White:
BUILDING 1
Current Progress-to-Date
- Foundation Excavation Operations Completed
- Continuous Foundation Footings & Grade Beams (Pour) Completed
- Foundation Damp/Waterproofing Completed
- In Progress: Underground Utilities
Upcoming Scope
- Foundation Backfill Operations & Concrete SOG Preparation
- Radiant Heat Installation & Concrete Slab-on-Grade (SOG)
BUILDING 4
Current Progress-to-Date
- Foundation Excavation Operations Completed
- Continuous Foundation Footings & Grade Beams (Pour) Completed
- Foundation Damp/Waterproofing Completed
- Underground Utilities Completed
- Foundation Backfill Operations Completed
- Radiant Heat Installation & Inspection Completed
- Concrete Slab-on-Grade (SOG) Completed
- In Progress: Prefabricated Wall Install – 1st Floor
Upcoming Scope
- Prefabricated Floor Panel/Wall Install – 2nd Floor
BUILDING 5
Current Progress-to-Date
- Foundation Excavation Operations Completed
- Continuous Foundation Footings & Grade Beams (Pour) Completed
- Foundation Damp/Waterproofing Completed
- Underground Electrical Utilities Completed
- In-Progress: Underground Plumbing Utilities & Backfill Operations
Upcoming Scope
- Concrete SOG Preparation & Radiant Heat Installation
- Radiant Heat Inspection & Concrete Slab-on-Grade (SOG)
BUILDING 6
Current Progress-to-Date
- Foundation Excavation Operations Completed
- Continuous Foundation Footings (Pour) Completed
- Foundation Damp/Waterproofing Completed
- Underground Electrical Utilities Completed
- In-Progress: Underground Plumbing Utilities & Backfill Operations
Upcoming Scope
- Concrete SOG Preparation & Radiant Heat Installation